Corbitt Residence Updates

Irma Chlepko Irma Chlepko

Rough-Ins & Stone Selections

Continuing with HVAC and plumbing rough-in installation—things are really starting to take shape! Stone samples are installed and ready for the final decision. Excited to see these design choices come together!

Read More
Irma Chlepko Irma Chlepko

HVAC & Plumbing Rough-Ins Underway

Mechanical installations are underway as the HVAC crew continues ductwork installation and the plumbing crew progresses on system rough-ins. These critical steps ensure comfort and efficiency throughout the home and move us closer to the next stage of construction.

Read More
Irma Chlepko Irma Chlepko

Shaping What’s to Come

The roof is taking shape, our stone sample is complete, and plumbing drains are now installed. Each of these steps lays the foundation for the craftsmanship and luxury design to come. The vision is moving from plans to reality, and the transformation is well underway!

Read More
Irma Chlepko Irma Chlepko

Framing Progress with Touch-Ups & Changes

Framing continues to move forward with touch-ups and a few design adjustments along the way. The HVAC team has wrapped up roof penetrations in preparation for shingles, and permanent stairs are now in place. Every step brings this home closer to the finished vision.

Read More
Irma Chlepko Irma Chlepko

Mechanical Rough-In and Interior Progress Underway

Progress continues on site! HVAC rough-in is underway, cornice work has been completed, and framers are wrapping up their frame punch. Plumbers have started their rough-in work, and the fireplace installation is now in progress. Steady steps forward as we move into the next phase of construction.

Read More
Irma Chlepko Irma Chlepko

Framing Touch-Ups & Window Deliveries in Motion

Miscellaneous touch-up framing is in progress as we prep for the next phase. Window and slider deliveries are rolling in, with one full window package already on site. Keeping momentum strong as we move forward!

Read More
Irma Chlepko Irma Chlepko

Framing Nearing the Finish Line

We’re just days away from completing framing—and the craftsmanship is nothing short of impressive. Every line, angle, and beam is coming together beautifully!

Read More
Irma Chlepko Irma Chlepko

Framing Milestone: Roof Structure Takes Shape

Framing is in full swing on site, and we’ve just started roof framing! The structure is really taking shape, and every beam and board brings us one step closer to the finished home. Excited to see this progress unfold!

Read More