Stegeman Residence Updates

Irma Chlepko Irma Chlepko

Inside Finishing, Outside Trenching

While our inside crew handles miscellaneous finishing touches, the outside team is hard at work digging a trench for the low-voltage communication link. This essential step will ensure smooth installation of data and communication lines, keeping the project connected and up-to-date with the latest tech.

Teamwork in action — making progress on all fronts!

Read More
Irma Chlepko Irma Chlepko

Interior Progress + Garage Details Coming Together

Interior progress is stacking up: hardwood floors are being installed, the elevator is going in, and electrical trim work continues. Over in the detached garage, ceiling beams are being set in place—adding structure and style as we move closer to completion.

Read More
Irma Chlepko Irma Chlepko

Dialing It In: Plumbing, HVAC & Electrical Progress

Progress continues on-site this week as we check off more critical finish tasks:

✔️ Plumbing trim install is underway—final fixtures and details coming together
✔️ HVAC crews are setting the AC units to keep things cool
✔️ Electrical trim and punch work are in motion, tying up the final connections

Another step closer to the finish line. More updates coming soon!

Read More
Irma Chlepko Irma Chlepko

Let the Light In!

This week, the big sliding glass doors are in—bringing in natural light and opening up the views! Inside, we’re continuing to focus on cabinet installation as the interior starts to come to life.

Read More
Irma Chlepko Irma Chlepko

Cabinet Installation & Countertops Coming Up!

Progress continues on both the interior and exterior of the home! We’re hard at work with miscellaneous tasks, including cabinet installation, and are excited to share that countertops are next on the schedule.

Read More
Irma Chlepko Irma Chlepko

Final Trim & Hardware Install Underway

Final electrical trim is going in, and door hardware is being installed throughout the home. These finishing touches are what bring the space to life—function meets form as we move closer to completion.

Read More
Irma Chlepko Irma Chlepko

Building the Ultimate Backyard Oasis

Pool installation is underway, with rebar in place and shaping up fast. Railings are installed, and our stone masons are fine-tuning their work for a flawless finish. Excited to see this project come together!

Read More
Irma Chlepko Irma Chlepko

Interior Finishes & Exterior Details Coming Together!

Interior details are coming together! The modern metal stair railing is installed, with wood handrails being fitted for a sleek finish. Tile and interior trim work are underway, while cabinets have been delivered and installation has begun. Outside, the exterior stone masonry is nearing completion, adding the perfect finishing touch to the façade.

Read More
Irma Chlepko Irma Chlepko

Utilities & Stonework Progress!

Laying the groundwork—literally! We’re digging and covering utility trench "umbilical cords" throughout the project, ensuring everything runs smoothly behind the scenes. Meanwhile, the exterior stone install is pushing forward, bringing texture and character to the build. Big progress on all fronts!

Read More
Irma Chlepko Irma Chlepko

Building Momentum: Decking, Tile, Brick & Utilities in Motion!

Things are moving fast on-site!

✅ Decking and porch ceiling installation are well underway, adding structure and style.

✅ Tile work is starting, bringing in those finishing touches.

✅ Interior brick is going up, adding character and depth.

✅ Trenching for utilities is in progress, keeping everything on track behind the scenes.

Read More
Irma Chlepko Irma Chlepko

Bringing It All Together: Rear Deck & Interior Progress!

The rear deck installation is underway, adding another exciting step to this build! Inside, the trim work is coming together, and the space is really starting to take shape. The wood ceiling adds warmth and character, perfectly complementing the large windows that will soon flood the room with natural light.

Read More
Irma Chlepko Irma Chlepko

Prepped for Precision: Trim Work Begins & Front Gate Installed!

Big strides on-site! Prime paint is complete, and trim materials have arrived, setting the stage for the next transformation. Trim work begins soon, bringing more definition and detail to the interiors. Plus, the front gate is officially installed, adding the perfect touch to the entrance!

Read More
Irma Chlepko Irma Chlepko

Shaping Spaces: Sheetrock Installation in Progress

The transformation continues! This week, we’re making steady progress with the sheetrock installation, bringing definition and structure to the interior spaces. Each step moves us closer to a finished look, and we can’t wait to see it all come together.

Read More
Irma Chlepko Irma Chlepko

Drywall Delivered: Installation Next Up!

We’ve just received the delivery of drywall, and now it’s time to move on to installation! Every step brings us closer to transforming this space into a dream home.

Read More