Beaver Residence Updates
Framing Progress & Roof Trusses Arrive
Framing is moving right along and we’re picking up momentum. Roof trusses have been delivered to the site, setting the stage for the next big step in the build. Great progress this week!
Framing Progress
Framing continues to take shape, and every day this home reveals a little more of what makes it special. One of our favorite features? The pickleball court—perfectly positioned to capture a beautiful, sweeping view of Lake Lanier.
More progress to come!
Framing in Full Swing
Framing is officially underway! This is the stage where the home begins to take shape—walls go up, rooms become defined, and the overall structure becomes visible. During framing, the crew builds the skeleton of the house using engineered lumber, setting precise measurements to ensure everything aligns with the architectural plans.
It’s one of the most exciting phases, transforming a foundation into a real, tangible home. Stay tuned as the structure continues to rise!
From Foundation to Form
Concrete garage slab is officially poured, and framing is now underway! It’s always exciting to see a design move from plans to structure — this is the phase where the home starts to take shape and you can really feel the spaces come to life.
From here, walls start rising, rooms begin to define themselves, and the vision becomes real.
More progress updates coming soon!
Preparing for Framing as the Foundation Cures!
While the foundation cures, we’re lining up lumber delivery to kick off the framing phase! This is where the structure truly starts to take shape — walls go up, rooms take form, and the home’s design begins to come to life. Exciting days ahead as we move from groundwork to framing!
Radiant Heating Checked and Garage Slab Next
Radiant heating plumbing is holding strong after the concrete slab pour — a key milestone for efficient, cozy heating throughout the home. Next up, the garage slab will be formed and poured next week, keeping the project moving forward!
Hydronic heating installation is complete. hillside tree clearing is wrapping up, and concrete pouring for the basement slab is now in progress. Each step brings this home closer to taking full shape — precision and progress from the ground up.
Heating Coils Installation – Why It Matters
The heating coils we’ve installed are part of the hydronic slab system, which will circulate warm water throughout the concrete slab. This system provides efficient, even heat for the home, keeping it cozy while reducing energy costs. Installing these coils correctly is crucial for both comfort and long-term performance—they’ll be fully embedded in the slab, ensuring durability and optimal heat distribution.
With this step complete, we’re ready to pour the slab and move the project closer to completion.
Heating Coils Up Next!
We’re prepped and ready for the heating coils to be installed! Once in place, we’ll be able to move forward with pouring the slab. Another key step in creating comfort and efficiency from the ground up.
Strength in the Foundation
Materials are delivered and we’re ready to start placing rebar before pouring the foundation! 💪🏡
Rebar (reinforcing steel) is what gives concrete its strength and durability—it helps prevent cracking and supports the structure for years to come. This step is all about creating a solid backbone for the home.
Exciting to see the foundation coming together from the ground up.
From Pipes to Pour: Next Step Slab Prep
Under-slab plumbing is now complete. Next up: preparing for the slab pour. Every step brings this home closer to taking shape from the ground up!
Plumbing Progress Underway!
Our team is hard at work with the under-slab plumbing, laying the foundation for all the essential systems in the home. Every pipe and connection is being carefully installed to ensure long-lasting quality and reliability. Excited to see the next steps take shape!
Underground Plumbing Underway
Our plumbing vendor is on site preparing everything to begin the underground plumbing phase. Every step brings us closer to a home built with precision, quality, and attention to detail!
Waiting on Sunshine to Move Forward
Rainy days have slowed things down on site — we’re holding off until the sun returns to help dry things out before moving on to the next phase.
Setting the Stage with Erosion Control
Erosion control underway on site — grading is complete, and our team has installed hay and silt fencing to keep everything in compliance and protected. Setting the foundation right from the start!
Backfill in Progress, Next Up: Under Slab Plumbing
Backfill has started and damp proofing is wrapping up. Once the top half of the walls are done, we’ll continue with backfill—aiming to complete everything by Tuesday. Next up: under slab plumbing! Progress is moving steady.
Waterproofing Complete on Pool Terrace Walls
Waterproofing is now complete on the retaining walls at this lakeside build. Each step forward brings us closer to transforming this space into a stunning outdoor retreat.
Foundation Damp Proofing in Progress
Foundation damp proofing is underway to protect the structure from moisture and ensure lasting durability. With just two weeks until backfill, the project is moving steadily forward. Excited to see the next steps take shape!
Solid Ground: Foundation Curing in Progress
Foundation concrete is currently curing on site 🧱🕒 — an essential step that takes time but sets the stage for everything to come. Not much happening visually right now, but this quiet phase is all about building strength and stability for what’s next!
Foundation Walls Are In!
We built and poured the foundation walls — officially setting the groundwork for what’s to come!
Big things start from the bottom up, and this home is no exception.