Beaver Residence Updates

Irma Chlepko Irma Chlepko

Backfill in Progress, Next Up: Under Slab Plumbing

Backfill has started and damp proofing is wrapping up. Once the top half of the walls are done, we’ll continue with backfill—aiming to complete everything by Tuesday. Next up: under slab plumbing! Progress is moving steady.

Read More
Irma Chlepko Irma Chlepko

Foundation Damp Proofing in Progress

Foundation damp proofing is underway to protect the structure from moisture and ensure lasting durability. With just two weeks until backfill, the project is moving steadily forward. Excited to see the next steps take shape!

Read More
Irma Chlepko Irma Chlepko

Solid Ground: Foundation Curing in Progress

Foundation concrete is currently curing on site 🧱🕒 — an essential step that takes time but sets the stage for everything to come. Not much happening visually right now, but this quiet phase is all about building strength and stability for what’s next!

Read More
Irma Chlepko Irma Chlepko

Foundation Walls Are In!

We built and poured the foundation walls — officially setting the groundwork for what’s to come!
Big things start from the bottom up, and this home is no exception.

Read More
Irma Chlepko Irma Chlepko

Excavation Wrapped – Foundation Ahead

Excavation is officially complete ✅ Next up: finishing out the rest of the foundation. Progress is moving right on schedule — more updates to come as we go vertical!

Read More
Irma Chlepko Irma Chlepko

Breaking Ground – Site Excavation in Full Swing

Earthwork is underway and the site is taking shape! Our excavation crew is hard at work carving out the footprint for what’s to come. It’s always exciting to see the transformation from raw terrain to build-ready ground.

Next up: prepping for foundation layout.

Read More
Irma Chlepko Irma Chlepko

Laying the Groundwork: Backfilling in Progress!

Another key step underway as we backfill around the foundation, ensuring stability and proper drainage for the build. Every stage brings us closer to the finished home—stay tuned for more updates as we keep moving forward!

Read More
Irma Chlepko Irma Chlepko

Building an Oasis: Pool & Brickwork Progress!

Massive pool and water features are making great strides, transforming this outdoor space into a true oasis. Plus, brickwork is coming along beautifully on the exterior of the retaining wall, adding both strength and style to the landscape.

Read More
Irma Chlepko Irma Chlepko

Shaping the Dream: Pool Walls Coming to Life!

Pool walls are going up! As you can see, the structure is starting to take shape with the foundation walls in place. The walls are critical in ensuring the pool's strength and durability, especially with the challenging slope and lakeside views. Once complete, this pool will seamlessly blend into the landscape, offering a perfect retreat. Exciting progress ahead!

Read More
Irma Chlepko Irma Chlepko

Foundation Reinforcement Begins: Rebar Has Arrived On Site!

Exciting progress on site! The rebar has arrived, setting the stage for some serious foundation work. This is a crucial step as we reinforce the structure to ensure strength and durability. Can't wait to see this project rise from the ground up!

Read More
Irma Chlepko Irma Chlepko

Setting the Stage: Retaining Wall Foundation Prepped for Concrete Pour!

Boxing up the retaining wall foundation is underway, getting everything set for the next big step: pouring the concrete! This stage is crucial for ensuring the strength and stability of the structure. Every detail counts as a solid foundation is prepared that will stand the test of time.

Read More
Irma Chlepko Irma Chlepko

Final Plans Approved – Moving to Production!

We’ve just wrapped up our Customer Redline Review (CRR) meeting, and we’re excited to share that the final plans are officially off to production! This is a major milestone in the project, bringing us one step closer to seeing our vision come to life.

With all approvals in place and every detail fine-tuned, the next phase of construction is just around the corner. We can't wait to watch this project continue to take shape and share the progress with you all.

Read More
Irma Chlepko Irma Chlepko

Pool Site Clearing Underway!

We're excited to announce that site clearing has officially begun for the pool. This marks the first step toward creating a stunning outdoor space.

Read More
Irma Chlepko Irma Chlepko

Permit Approved: Ready to Build!

We're thrilled to announce that the building permit was issued on 7/15! With all necessary permits now in hand, we’re ready to move full steam ahead.

Read More
Irma Chlepko Irma Chlepko

Permit Progress

The permit is currently moving through the Hall County system.

🔍 What's Next? We're waiting on the septic system approval, which requires a site visit from the environmental health department. This process can take about 3 weeks.

Read More