Beaver Residence Updates
Backfill in Progress, Next Up: Under Slab Plumbing
Backfill has started and damp proofing is wrapping up. Once the top half of the walls are done, we’ll continue with backfill—aiming to complete everything by Tuesday. Next up: under slab plumbing! Progress is moving steady.
Waterproofing Complete on Pool Terrace Walls




Waterproofing is now complete on the retaining walls at this lakeside build. Each step forward brings us closer to transforming this space into a stunning outdoor retreat.
Foundation Damp Proofing in Progress



Foundation damp proofing is underway to protect the structure from moisture and ensure lasting durability. With just two weeks until backfill, the project is moving steadily forward. Excited to see the next steps take shape!
Solid Ground: Foundation Curing in Progress





Foundation concrete is currently curing on site 🧱🕒 — an essential step that takes time but sets the stage for everything to come. Not much happening visually right now, but this quiet phase is all about building strength and stability for what’s next!
Foundation Walls Are In!










We built and poured the foundation walls — officially setting the groundwork for what’s to come!
Big things start from the bottom up, and this home is no exception.
Footings Approved — Concrete Coming Soon!


We passed our footing inspection with flying colors! Concrete is scheduled to be poured this afternoon — stay tuned as we bring the next phase of this build to life.
Excavation Wrapped – Foundation Ahead





Excavation is officially complete ✅ Next up: finishing out the rest of the foundation. Progress is moving right on schedule — more updates to come as we go vertical!
Breaking Ground – Site Excavation in Full Swing



Earthwork is underway and the site is taking shape! Our excavation crew is hard at work carving out the footprint for what’s to come. It’s always exciting to see the transformation from raw terrain to build-ready ground.
Next up: prepping for foundation layout.
Site Prep Underway — Getting Ready for the Next Phase!
Prepping the site and laying the groundwork for what’s next! Excited for the next steps as this project begins to take shape.
Laying the Groundwork: Backfilling in Progress!



Another key step underway as we backfill around the foundation, ensuring stability and proper drainage for the build. Every stage brings us closer to the finished home—stay tuned for more updates as we keep moving forward!
Building an Oasis: Pool & Brickwork Progress!




Massive pool and water features are making great strides, transforming this outdoor space into a true oasis. Plus, brickwork is coming along beautifully on the exterior of the retaining wall, adding both strength and style to the landscape.
Shaping the Dream: Pool Walls Coming to Life!


Pool walls are going up! As you can see, the structure is starting to take shape with the foundation walls in place. The walls are critical in ensuring the pool's strength and durability, especially with the challenging slope and lakeside views. Once complete, this pool will seamlessly blend into the landscape, offering a perfect retreat. Exciting progress ahead!
Foundation Reinforcement Begins: Rebar Has Arrived On Site!








Exciting progress on site! The rebar has arrived, setting the stage for some serious foundation work. This is a crucial step as we reinforce the structure to ensure strength and durability. Can't wait to see this project rise from the ground up!
Setting the Stage: Retaining Wall Foundation Prepped for Concrete Pour!



Boxing up the retaining wall foundation is underway, getting everything set for the next big step: pouring the concrete! This stage is crucial for ensuring the strength and stability of the structure. Every detail counts as a solid foundation is prepared that will stand the test of time.
Power Onsite and Foundation Pad Set: Progress Milestones Achieved



Exciting updates on the project! The site now has power at the street, and the massive foundation pad for the retaining wall is in place. Things are shaping up quickly!
Precision in Progress: Pool Foundation Wall Grading Underway






Pool foundation wall grading is in progress!
We're carefully shaping the area to ensure everything is perfectly leveled and ready for the next steps. Exciting times ahead as this project continues to take shape.
Final Plans Approved – Moving to Production!
We’ve just wrapped up our Customer Redline Review (CRR) meeting, and we’re excited to share that the final plans are officially off to production! This is a major milestone in the project, bringing us one step closer to seeing our vision come to life.
With all approvals in place and every detail fine-tuned, the next phase of construction is just around the corner. We can't wait to watch this project continue to take shape and share the progress with you all.
Pool Site Clearing Underway!



We're excited to announce that site clearing has officially begun for the pool. This marks the first step toward creating a stunning outdoor space.
Permit Approved: Ready to Build!
We're thrilled to announce that the building permit was issued on 7/15! With all necessary permits now in hand, we’re ready to move full steam ahead.
Permit Progress
The permit is currently moving through the Hall County system.
🔍 What's Next? We're waiting on the septic system approval, which requires a site visit from the environmental health department. This process can take about 3 weeks.