Aldridge Residence Updates

Irma Chlepko Irma Chlepko

Cleared to Pour

Slab inspection is officially passed ✔️ and we’re cleared to move forward. The site is prepped, reinforcements are in place, and we’re ready to pour concrete—marking a major milestone in the build.

From here, things start moving fast as the foundation takes shape.

Read More
Irma Chlepko Irma Chlepko

Under-slab plumbing completed

Before the concrete is poured, every drain line, vent, and water supply is carefully laid out and installed beneath the slab. This critical phase ensures bathrooms, kitchens, and utility spaces are positioned exactly as designed—leaving no room for shortcuts.

With under-slab plumbing complete and verified, the foundation is officially ready for the next steps in construction.

Read More
Irma Chlepko Irma Chlepko

Forms Set for Slab Pour

We’re prepping for a major milestone—slab pour day. The crew is setting forms to define the exact shape and elevation of the foundation, ensuring everything is level, square, and ready for concrete. Once complete, this creates a strong, stable base that the entire home will be built on. One step closer to bringing this home out of the ground!

Read More
Irma Chlepko Irma Chlepko

Site Prep & Clearing Underway

Grading is underway and our crew is moving through the lot with tree removal and debris cleanup. Clearing the site is the first big step toward bringing this new custom home to life — and we’re off to a strong start!

More updates coming soon as we continue preparing the land for construction. 💬 Let us know what part of the build you enjoy seeing most!

Read More
Irma Chlepko Irma Chlepko

Project Start: Permits, Power & Lot Clearing

It’s an exciting start on this new homesite! The lot sign and permit box are now installed, marking the official beginning of construction activity. ✔️

The temporary power (T-pole) inspection is also underway, an important step to bring electrical service to the site so crews can begin work efficiently.

Lot clearing has started as well—removing brush, debris, and small trees to prepare the property for grading and foundation work. This phase sets the stage for everything that comes next.

Big things are ahead on this build!

Read More
Irma Chlepko Irma Chlepko

Permit Approved

Great news—our building permit has been approved! This milestone clears the way to move full speed ahead and keep the project progressing on schedule. Excited to continue bringing this home to life.

Read More
Irma Chlepko Irma Chlepko

Curating the Palette

Getting ready for our client color session.
This is one of our favorite stages — where finishes, tones, and textures come together to reflect the homeowner’s personal style. From paint palettes to tile and cabinet selections, this is where the home starts to feel uniquely theirs.

Every detail matters, and we’re excited to help bring their vision to life

Read More
Irma Chlepko Irma Chlepko

Final Plans in Motion

Customer redlines are complete, and the finalized plans are now in production!
This stage is where every detail is fine-tuned — ensuring the home design perfectly matches the client’s vision before construction begins.

We’re one step closer to breaking ground, and we can’t wait to see this project come to life!

Read More